Dec 2026
Possession
22.7%
Built
0
Complaints
0
Units
High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 22.7%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52100004404
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026
Construction
22.7% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drains15%
Landscaping & Tree Planting15%
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Aug 2017
Floors
11

Buyer community

Connect with other buyers and owners of RAJESH GOLDEN HOMES โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching RAJESH GOLDEN HOMES. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.