Under construction

CRYSTAL SPRING

by KISHANKUMAR JUGALKISHOR KEDIA

GUT NO 302 AND GUT NO 292, Karla, 410405

Dec 2029
Possession
88.3%
Built
13
Complaints
1
Units
High risk
  • Possession delayed ~6 yrs. Originally promised Nov 2023, now proposed Dec 2029 per the RERA filing.
  • 13 RERA complaints. 13 complaint records are disclosed against this project on MahaRERA.

Official RERA facts

Registration
P52100004437
Status
Ongoing
Stage
Certificate Signed
Possession
December 2029originally November 2023
Construction
88.3% complete
Units sold
0 of 1

RERA complaint record13 records

Complaint data not yet synced for this project.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths80%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drains80%
Landscaping & Tree Planting80%
Street Lighting70%
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirements80%
Electrical meter room, sub-station, receiving station90%
Aggregate area of recreational Open Spacenot started
Open Parking90%

Building & registration

RERA registered
Aug 2017
Floors
2
Unit mix
1 res ยท 0 comm

Buyer community

Connect with other buyers and owners of CRYSTAL SPRING โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching CRYSTAL SPRING. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.