Under construction

Prabodhan Apartments

by Pinnac Housing Private Limited

Final Plot No 64 CTS No 105/9, Prabhat Road, 411004

Aug 2019
Possession
59.2%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Aug 2019) has passed with construction at 59.2%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Aug 2019 per the RERA filing.

Official RERA facts

Registration
P52100004585
Status
Ongoing
Stage
Certificate Signed
Possession
August 2019originally August 2018
Construction
59.2% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Covered Mechanical dependent stack parkingnot started
Liftnot started
Compound wall with main gatenot started
Power bakc upnot started

Building & registration

RERA registered
Aug 2017
Floors
6

Buyer community

Connect with other buyers and owners of Prabodhan Apartments โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Prabodhan Apartments. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.