Under construction

METRO JAZZ

by BALAJI REALTY

SURVEY NO 12 PART 1, Baner, 411045

Sept 2020
Possession
76.4%
Built
1
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Mar 2019, now proposed Sept 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Sept 2020) has passed with construction at 76.4%.

Official RERA facts

Registration
P52100004597
Status
Ongoing
Stage
Certificate Signed
Possession
September 2020originally March 2019
Construction
76.4% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths75%
Water Supply75%
Sewerage (Chamber, Lines, Septic Tank , STP)70%
Storm Water Drains90%
Landscaping & Tree Planting75%
Street Lighting75%
Community Buildings90%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting70%
Energy managemcntnot started
Fire protection and fire safety requirements25%
Electrical meter room, sub-station, receiving station60%
Open Parking10%

Building & registration

RERA registered
Aug 2017
Floors
15

Buyer community

Connect with other buyers and owners of METRO JAZZ โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching METRO JAZZ. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.