Sept 2020
Possession
76.4%
Built
1
Complaints
0
Units
High risk
- Possession delayed ~2 yrs. Originally promised Mar 2019, now proposed Sept 2020 per the RERA filing.
- Possession date passed. The proposed possession date (Sept 2020) has passed with construction at 76.4%.
Official RERA facts
- Registration
- P52100004597
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- September 2020originally March 2019
- Construction
- 76.4% complete
- Units sold
- 0 of 0
RERA complaint record1 record
- ComplaintCC00500000009590118 Aug 2021Rohit Prasade vs Nitin Chitodkarorder CC005-95901 dtd 22-09-2021.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths75%
Water Supply75%
Sewerage (Chamber, Lines, Septic Tank , STP)70%
Storm Water Drains90%
Landscaping & Tree Planting75%
Street Lighting75%
Community Buildings90%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting70%
Energy managemcntnot started
Fire protection and fire safety requirements25%
Electrical meter room, sub-station, receiving station60%
Open Parking10%
Building & registration
- RERA registered
- Aug 2017
- Floors
- 15
Buyer community
Connect with other buyers and owners of METRO JAZZ โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching METRO JAZZ. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.