Mar 2024
Possession
42.3%
Built
8
Complaints
0
Units
High risk
- Possession delayed ~4 yrs. Originally promised Dec 2019, now proposed Mar 2024 per the RERA filing.
- 8 RERA complaints. 8 complaint records are disclosed against this project on MahaRERA.
- Possession date passed. The proposed possession date (Mar 2024) has passed with construction at 42.3%.
- Promised amenities not started. Clubhouse, Landscaped Garden, Kids Play Area are at 0% build with possession due Mar 2024 per the RERA filing.
Official RERA facts
- Registration
- P52100004883
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- March 2024originally December 2019
- Construction
- 42.3% complete
- Units sold
- 0 of 0
RERA complaint record8 records
- ComplaintCC126012407 Mar 2026NAVNEET MAHADEV AHIRE vs MAA SANKALP BUILDCON
- ComplaintCC1240121323 Dec 2024ZAHER MUSTAQUE AHMED MOHAMMED ALI PAREMPALLI vs MAA SANKALP BUILDCONCT order CC12401213.pdf on MahaRERA
- ComplaintCC00500000032063111 Apr 2024Prasad Deepak Mane vs M/s. Maa Sankalp BuildconFinal Order 320631.pdf on MahaRERA
- ComplaintCC00500000017772629 Oct 2022MAA SANKALP BUILDCON vs MR. PRATIK SUDHENDRA SHROTRIFinal Order 177726.pdf on MahaRERA
- ComplaintCC00500000017772729 Oct 2022MAA SANKALP BUILDCON vs MRS. VRUSHALI ABHISHEK JOSHIMAA SANKALP BUILDCON.pdf on MahaRERA
- ComplaintCC00500000015726727 Jun 2022PRATIK SUDHENDRA SHROTRI vs MAA SANKALP BUILDOCONsr 42 of 26 april do signed.pdf on MahaRERA
- Misc. applicationCC00500000005390217 Feb 2020SMT. PALLAVI MANOHAR SALUNKE vs Shri Vishal Suresh PawarOrder of Pallavi Salunke.pdf on MahaRERA
- ComplaintCC00500000005390217 Feb 2020SMT. PALLAVI MANOHAR SALUNKE vs Shri Vishal Suresh Pawar53902.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
WATER BODYnot started
CHILDREN PLAY AREAnot started
Building & registration
- RERA registered
- Aug 2017
- Floors
- 12
Buyer community
Connect with other buyers and owners of SAI DWARKA PHASE 2 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SAI DWARKA PHASE 2. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.