Jun 2018
Possession
82.1%
Built
0
Complaints
0
Units
Caution
- Possession date passed. The proposed possession date (Jun 2018) has passed with construction at 82.1%.
Official RERA facts
- Registration
- P52100005122
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2018
- Construction
- 82.1% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths75%
Water Supply70%
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drains90%
Landscaping & Tree Planting25%
Street Lightingnot started
Community Buildings98%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting70%
Energy managemcntnot started
Fire protection and fire safety requirements80%
Electrical meter room, sub-station, receiving station60%
Open Parking10%
Building & registration
- RERA registered
- Aug 2017
- Floors
- 16
Buyer community
Connect with other buyers and owners of METRO JAZZ โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching METRO JAZZ. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.