Shubhankar Durvaa Phase 2MahaRERA P52100005238
29/1/1, Dhanori, 411015
Jun 2022
Possession
81.8%
Built
4
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Jun 2022) has passed with construction at 81.8%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2022 per the RERA filing.
Official RERA facts
- Registration
- P52100005238
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2022originally June 2021
- Construction
- 81.8% complete
- Units sold
- 0 of 0
RERA complaint record4 records
- ComplaintCC00500000034071314 Apr 2024Farheen Imtiyaz Shaikh vs ATUL DYNASHWAR BHAIRATOrder of Farheen Shaikh.pdf on MahaRERA
- ComplaintCC0050000001980649 Jan 2023Juber Mushtaque Ahmed vs Atul BahiratOrder of Juber Mushtaque Ahmed vs Atul Bahirat (2).pdf on MahaRERA
- ComplaintCC0050000001065772 Feb 2022RAHUL NEELKANTH DESHMUKH vs SHUBHANKAR DEVELOPERS THROUGH ATUL DYANESHWAR BAHIRATOrder of Rahul Neelkanth Deshmukh vs Shubhankar Developers (1).pdf on MahaRERA
- ComplaintCC00500000000021011 Sept 2017RAHUL NEELKANTH DESHMUKH vs ATUL DYANESHWAR BAHIRAT, PROPRITOR OF SHUBHANKAR DEVELOPEMENTS210.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Building & registration
- RERA registered
- Aug 2017
- Floors
- 12
Buyer community
Connect with other buyers and owners of Shubhankar Durvaa Phase 2 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Shubhankar Durvaa Phase 2. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.