Under construction

Vertical Oriana Phase III

by Vertical Infra

Survey No7/1A 2A 2B, Mundhwa, 411036

Dec 2021
Possession
51.1%
Built
1
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 51.1%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2021 per the RERA filing.

Official RERA facts

Registration
P52100005269
Status
Ongoing
Stage
Certificate Signed
Possession
December 2021originally January 2021
Construction
51.1% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths40%
Water Supply30%
Sewerage (Chamber, Lines, Septic Tank , STP)35%
Storm Water Drains40%
Landscaping & Tree Plantingnot started
Street Lighting25%
Community Buildingsnot started
Solid Waste Management And Disposal85%
Water conservation /Rain water harvesting20%
Fire protection and fire safety requirements10%
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started
Open Parking10%
Entertainment Lounge and Library90%
Garbage Chutenot started
Gas Banknot started
Solar Water Heater Systemnot started
Lift Installationnot started

Building & registration

RERA registered
Aug 2017
Floors
18

Buyer community

Connect with other buyers and owners of Vertical Oriana Phase III โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Vertical Oriana Phase III. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.