CONSTRUCTION OF 648 NOS EWS TS, 620 LIG TS UNDER PH2 AT MAHALUNGE TAL KHED DIST PUNE

by Pune Housing & Area Development Board

44PT, 49PT, 129PT, 130/1/A, 130/1/B, 130/2, 130/3PT, 130/4PT, Mahalunge, 410501

Dec 2020
Possession
24.5%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Jun 2019, now proposed Dec 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2020) has passed with construction at 24.5%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2020 per the RERA filing.
MulundUpper-mid

Leafy eastern-suburb favourite with big redevelopment supply.

Growth drivers:
Eastern Express Highway, proposed Goregaon–Mulund link, mall belt.
Who buys here:
Eastern-suburb families upgrading within the area.

PropPin area guide — editorial, not a RERA disclosure.

Official RERA facts

Registration
P52100005293
Status
Ongoing
Stage
Certificate Signed
Possession
December 2020originally June 2019
Construction
24.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supply75%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
17

Buyer community

Connect with other buyers and owners of CONSTRUCTION OF 648 NOS EWS TS, 620 LIG TS UNDER PH2 AT MAHALUNGE TAL KHED DIST PUNE — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching CONSTRUCTION OF 648 NOS EWS TS, 620 LIG TS UNDER PH2 AT MAHALUNGE TAL KHED DIST PUNE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.