Under construction

Purva Silversands Phase 2

by Pune Projects LLP

Sy No 9 to 14, Keshavnagar, 410036

Oct 2026
Possession
86.2%
Built
23
Complaints
336
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Nov 2022, now proposed Oct 2026 per the RERA filing.
  • 23 RERA complaints. 23 complaint records are disclosed against this project on MahaRERA.
GoregaonUpper-mid

Film City flank with large integrated townships on both flanks.

Growth drivers:
Oberoi/NESCO belt, Metro 7, Western Express Highway offices.
Who buys here:
Upgraders wanting township amenities without Powai prices.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P52100005377
Status
Ongoing
Stage
Certificate Signed
Possession
October 2026originally November 2022
Construction
86.2% complete
Units sold
306 of 336

RERA complaint record23 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)95%
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
22
Unit mix
336 res ยท 0 comm
Architect
Rana Ram Ram

Buyer community

Connect with other buyers and owners of Purva Silversands Phase 2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Purva Silversands Phase 2. Real notes from real buyers beat any brochure.