Kingston Atlantis A1 and A2 Building

by Vedant Landmarks

39/6, 39/7, 39/11, MOHAMMADWADI, 411028

Jun 2026
Possession
95.5%
Built
25
Complaints
0
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Jun 2022, now proposed Jun 2026 per the RERA filing.
  • 25 RERA complaints. 25 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 95.5%.

Official RERA facts

Registration
P52100005525
Status
Ongoing
Stage
Certificate Signed
Possession
June 2026originally June 2022
Construction
95.5% complete
Units sold
0 of 0

RERA complaint record25 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Open Parkingdone

Building & registration

RERA registered
Aug 2017
Floors
15

Buyer community

Connect with other buyers and owners of Kingston Atlantis A1 and A2 Building โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Kingston Atlantis A1 and A2 Building. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.