METRO JAZZ
SURVEY NO 12 PART 1, Mumbai Pune Express Highway, 411045
Dec 2018
Possession
94.5%
Built
0
Complaints
0
Units
Caution
- Possession date passed. The proposed possession date (Dec 2018) has passed with construction at 94.5%.
Official RERA facts
- Registration
- P52100005925
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2018
- Construction
- 94.5% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supply60%
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Storm Water Drains85%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting75%
Energy managemcntnot started
Fire protection and fire safety requirements75%
Electrical meter room, sub-station, receiving station30%
Open Parking10%
Building & registration
- RERA registered
- Aug 2017
- Floors
- 15
Buyer community
Connect with other buyers and owners of METRO JAZZ โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching METRO JAZZ. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.