All RERA projects
๐๏ธ
Aug 2018
Possession
100%
Built
3
Complaints
0
Units
Clean record
No delays, complaints or enforcement actions in the official disclosures we track.
Official RERA facts
- Registration
- P52100006218
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- August 2018
- Construction
- 100% complete
- Units sold
- 0 of 0
RERA complaint record3 records
- ComplaintCC0050000000115987 Jun 2018G T DEVELOPERS vs PRAVIN UTTAMRAO KAKADEG t develoers.pdf on MahaRERA
- ComplaintCC00500000001108926 Feb 2018Brahmanand Kadam vs G. T. DevelopersScanned Order CC005_11089.pdf on MahaRERA
- Misc. applicationCC00500000001108926 Feb 2018Brahmanand Kadam vs G. T. Developers
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingdone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Building & registration
- RERA registered
- Aug 2017
- Floors
- 12
Buyer community
Connect with other buyers and owners of Mangal Dhaara โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Mangal Dhaara. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.