Under construction

SAI EMRALD

by SAIESHWAR PROJECTSS

CTS NO 362 AND 363, Pune (M Corp.), 411030

Dec 2023
Possession
99.2%
Built
1
Complaints
0
Units
High risk
  • Possession delayed ~5 yrs. Originally promised Dec 2018, now proposed Dec 2023 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 99.2%.

Official RERA facts

Registration
P52100006251
Status
Ongoing
Stage
Certificate Signed
Possession
December 2023originally December 2018
Construction
99.2% complete
Units sold
0 of 0

RERA complaint record1 record

  • ComplaintCC0050000000644766 Aug 2020
    Shantaram Ramchandra Patil vs Vijay Narayan Jalan

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply60%
Sewerage (Chamber, Lines, Septic Tank , STP)60%
Storm Water Drainsnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station40%

Building & registration

RERA registered
Aug 2017
Floors
8

Buyer community

Connect with other buyers and owners of SAI EMRALD โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAI EMRALD. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.