  • Possession date passed. The proposed possession date (Aug 2019) has passed with construction at 52.7%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Aug 2019 per the RERA filing.

Official RERA facts

Registration
P52100006431
Status
Ongoing
Stage
Certificate Signed
Possession
August 2019
Construction
52.7% complete
Units sold
0 of 0

RERA complaint record1 record

  • ComplaintCC00500000001078631 Dec 2017
    Nitin Gunjan/Anshu Kumar/Vinay Pati vs Dilip Bandal/Ram Chandra Kudale
    cc10786.pdf on MahaRERA

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Planting70%
Street Lightingdone
Community Buildingsnot started
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
13

Buyer community

Connect with other buyers and owners of VANASHREE E โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching VANASHREE E. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.