Under construction

PRISTINE VILLA PHASE III

by ATHARV DEVELOPERS

GUT NO 488 AND 490 P, Karla, 410405

Dec 2021
Possession
25.9%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2019, now proposed Dec 2021 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 25.9%.

Official RERA facts

Registration
P52100006460
Status
Ongoing
Stage
Certificate Signed
Possession
December 2021originally December 2019
Construction
25.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths70%
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)40%
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lighting50%
Water conservation /Rain water harvesting10%
Electrical meter room, sub-station, receiving station70%
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
2

Buyer community

Connect with other buyers and owners of PRISTINE VILLA PHASE III โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching PRISTINE VILLA PHASE III. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.