SAMRUDDHI ISHA

by SAMRUDDHI ENTERPRISES

CTS NO 1687, 1688 AND 1689, KIVALE, 412101

Dec 2023
Possession
70.9%
Built
7
Complaints
0
Units
High risk
  • Possession delayed ~5 yrs. Originally promised Dec 2018, now proposed Dec 2023 per the RERA filing.
  • 7 RERA complaints. 7 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 70.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2023 per the RERA filing.

Official RERA facts

Registration
P52100006794
Status
Ongoing
Stage
Certificate Signed
Possession
December 2023originally December 2018
Construction
70.9% complete
Units sold
0 of 0

RERA complaint record7 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply25%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
POWER BACKUPnot started
VIDEO DOOR PHONEnot started
SOLAR WATER HEATING SYSTEMnot started

Building & registration

RERA registered
Aug 2017
Floors
9

Buyer community

Connect with other buyers and owners of SAMRUDDHI ISHA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAMRUDDHI ISHA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.