Under construction

GAYATRREE LANDMARK PHASE II

by GAYATRREE SKYSCRAPERS

S NO 21/1C, Dange chowk, 411033

Dec 2022
Possession
44.8%
Built
2
Complaints
0
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2018, now proposed Dec 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 44.8%.

Official RERA facts

Registration
P52100007004
Status
Ongoing
Stage
Certificate Signed
Possession
December 2022originally December 2018
Construction
44.8% complete
Units sold
0 of 0

RERA complaint record2 records

  • ComplaintCC0050000000648064 Nov 2020
    SANJAY BHOIR, JAYA BHOIR AND SEEMA BHOIR vs M/s Gayatrree Skyscrapers pvt ltd
    CC005000000064806.pdf on MahaRERA
  • ComplaintCC0050000000334915 Oct 2019
    MR SANJAY GULAB BHOIR, MRS JAYA GULAB BHOIR AND MRS SEEMA SANJAY BHOIR vs GAYATRREE SKYSCRAPERS patnership firm, MR VISHWANATHVARMA, MRS DIPIKA VARMA AND OTHERS
    33491-20032020145229.pdf on MahaRERA

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsdone
Water conservation /Rain water harvestingdone
Energy managemcnt70%
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Open Parkingdone

Building & registration

RERA registered
Aug 2017
Floors
12

Buyer community

Connect with other buyers and owners of GAYATRREE LANDMARK PHASE II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching GAYATRREE LANDMARK PHASE II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.