Under construction

MARVEL ARCO E BUILDING

by MARVEL SIGMA HOMES PRIVATE LIMITED

S.NO 176/1,176/2/1,176/2/2, Hadapsar, 411028

Dec 2018
Possession
96.8%
Built
3
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2018) has passed with construction at 96.8%.

Official RERA facts

Registration
P52100007022
Status
Ongoing
Stage
Certificate Signed
Possession
December 2018
Construction
96.8% complete
Units sold
0 of 0

RERA complaint record3 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supply95%
Sewerage (Chamber, Lines, Septic Tank , STP)85%
Storm Water Drains90%
Landscaping & Tree Planting95%
Street Lighting95%
Community Buildings75%
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting65%
Energy managemcnt30%
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving station95%
Aggregate area of recreational Open Space80%

Building & registration

RERA registered
Aug 2017
Floors
17

Buyer community

Connect with other buyers and owners of MARVEL ARCO E BUILDING โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MARVEL ARCO E BUILDING. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.