Star Woods Phase I

by Vaishnavi Space Creator

58/2/2, Tathwade, 411033

Mar 2018
Possession
50%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2018) has passed with construction at 50%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2018 per the RERA filing.

Official RERA facts

Registration
P52100007153
Status
Ongoing
Stage
Certificate Signed
Possession
March 2018
Construction
50% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Electrical meter room, sub-station, receiving stationnot started
Compoundwall and Gate75%

Building & registration

RERA registered
Aug 2017
Floors
6

Buyer community

Connect with other buyers and owners of Star Woods Phase I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Star Woods Phase I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.