All RERA projects
๐๏ธ
Under construction
Kul Utsav Phase I - Building D
Sr No 30 H No 2B/2 Sr No 30 H No 7 Sr No 31 H no 31/3, pune, 411048
Oct 2020
Possession
90.9%
Built
1
Complaints
0
Units
High risk
- Possession delayed ~1 yr. Originally promised May 2019, now proposed Oct 2020 per the RERA filing.
- Possession date passed. The proposed possession date (Oct 2020) has passed with construction at 90.9%.
Official RERA facts
- Registration
- P52100007160
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- October 2020originally May 2019
- Construction
- 90.9% complete
- Units sold
- 0 of 0
RERA complaint record1 record
- ComplaintCC0050000000540921 Mar 2020Uday Rajaram Jagadale vs Kumar Builders Partners Kumar Hus Corp,Kumar Urban Dev,Sukumar Realters And capital Pvt ltd.LOP ORDER 0054092.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Open Parkingdone
Building & registration
- RERA registered
- Aug 2017
- Floors
- 15
Buyer community
Connect with other buyers and owners of Kul Utsav Phase I - Building D โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Kul Utsav Phase I - Building D. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.