Under construction

Platinum Park Phase I

by Ranjeet Property Developers India Pvt. Ltd.

37/2/1 40/2/1 40/2/2, UNDRI, 411060

Dec 2019
Possession
98.5%
Built
5
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2019) has passed with construction at 98.5%.

Official RERA facts

Registration
P52100007249
Status
Ongoing
Stage
Certificate Signed
Possession
December 2019originally December 2018
Construction
98.5% complete
Units sold
0 of 0

RERA complaint record5 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths90%
Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drains90%
Landscaping & Tree Planting50%
Street Lighting90%
Treatment And Disposal Of Sewage And Sullage Water90%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting80%
Energy managemcntnot started
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving station90%
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
13

Buyer community

Connect with other buyers and owners of Platinum Park Phase I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Platinum Park Phase I. Real notes from real buyers beat any brochure.