Under construction

VISION WOODS 1 PHASE II

by SHUBBAN REALTORS

336, Jambhul, 412105

Apr 2018
Possession
87.2%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Apr 2018) has passed with construction at 87.2%.

Official RERA facts

Registration
P52100007352
Status
Ongoing
Stage
Certificate Signed
Possession
April 2018originally March 2018
Construction
87.2% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsnot started
Landscaping & Tree Planting80%
Street Lighting80%
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving station50%
COMPOUND WALL50%

Building & registration

RERA registered
Aug 2017
Floors
1

Buyer community

Connect with other buyers and owners of VISION WOODS 1 PHASE II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching VISION WOODS 1 PHASE II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.