MADHUBAN
Gat No 61, Dudulgaon, Pimpri Chinchawad (M Corp.), 412105
Dec 2026
Possession
93.3%
Built
0
Complaints
35
Units
High risk
- Possession delayed ~5 yrs. Originally promised Dec 2021, now proposed Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P52100007662
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2021
- Construction
- 93.3% complete
- Units sold
- 32 of 35
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)40%
Storm Water Drains30%
Landscaping & Tree Planting20%
Water conservation /Rain water harvesting40%
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Building & registration
- RERA registered
- Aug 2017
- Floors
- 6
- Unit mix
- 35 res ยท 0 comm
- Architect
- RAJAS DESIGNERS
Buyer community
Connect with other buyers and owners of MADHUBAN โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching MADHUBAN. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.