Mar 2021
Possession
38.2%
Built
1
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Mar 2021) has passed with construction at 38.2%.
Official RERA facts
- Registration
- P52100008510
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2021originally March 2020
- Construction
- 38.2% complete
- Units sold
- 0 of 0
RERA complaint record1 record
- ComplaintCC00500000004370224 Nov 2019Hitendra Singh vs Utin ChauhanOrder of Hitendra Singh.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsdone
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Water5%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Building & registration
- RERA registered
- Aug 2017
- Floors
- 12
Buyer community
Connect with other buyers and owners of Beverly Hills - Building F โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Beverly Hills - Building F. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.