Under construction

SAPPHIRE

by Sai Nisarg Developers LLP

195/1/2/1961to8plotno1to18plot no122 to 128, Pimpri Chinchawad (M Corp.), 411033

Mar 2022
Possession
74.5%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2022) has passed with construction at 74.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2022 per the RERA filing.

Official RERA facts

Registration
P52100008695
Status
Ongoing
Stage
Certificate Signed
Possession
March 2022
Construction
74.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths70%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)70%
Storm Water Drains70%
Landscaping & Tree Plantingnot started
Street Lighting70%
Water conservation /Rain water harvesting70%
Fire protection and fire safety requirements70%
Electrical meter room, sub-station, receiving station70%
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
11

Buyer community

Connect with other buyers and owners of SAPPHIRE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAPPHIRE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.