Under construction

Shinde Darade Complex

by SHINDE DARADE ASSOCIATES

Gat No 186 1, Plot No 27 part, Jalochi, 413102

Nov 2019
Possession
32.3%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Nov 2019) has passed with construction at 32.3%.
Vile Parle East / AirportUpper-mid

Institutional belt (colleges, airport) with steady society redevelopment.

Growth drivers:
Airport economy, Metro 3, education cluster.
Who buys here:
Airline/airport professionals, Parle loyalists.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P52100008723
Status
Ongoing
Stage
Certificate Signed
Possession
November 2019
Construction
32.3% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply25%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Aug 2017
Floors
5

Buyer community

Connect with other buyers and owners of Shinde Darade Complex โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Shinde Darade Complex. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.