Under construction

Jitendra Heritage - E 2 Building - Phase - 1

by Jitendra Constructions

Survey No 5/4A, 4B, 5, 5/7, Pashan, 411045

Dec 2030
Possession
41.5%
Built
0
Complaints
1
Units
High risk
  • Possession delayed ~7 yrs. Originally promised Aug 2023, now proposed Dec 2030 per the RERA filing.
Vasai–VirarValue

The western line's volume market — dense affordable towers past Mira Road.

Growth drivers:
Suburban rail quadrupling, coastal-road extensions, MMR's biggest affordable pipeline.
Who buys here:
Budget-first buyers who commute the western line.

PropPin area guide — editorial, not a RERA disclosure.

Official RERA facts

Registration
P52100009234
Status
Ongoing
Stage
Certificate Signed
Possession
December 2030originally August 2023
Construction
41.5% complete
Units sold
1 of 1

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supply40%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Aug 2017
Floors
7
Unit mix
1 res · 0 comm

Buyer community

Connect with other buyers and owners of Jitendra Heritage - E 2 Building - Phase - 1 — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching Jitendra Heritage - E 2 Building - Phase - 1. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.