PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SWARGANDH

by PRIDE PROPERTIES & INFRASTRUCTURE

88/4/138/161, Gujrat colony, 411038

Oct 2020
Possession
81.8%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Nov 2018, now proposed Oct 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Oct 2020) has passed with construction at 81.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2020 per the RERA filing.

Official RERA facts

Registration
P52100009418
Status
Ongoing
Stage
Certificate Signed
Possession
October 2020originally November 2018
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Aug 2017
Floors
5

Buyer community

Connect with other buyers and owners of SWARGANDH โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SWARGANDH. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.