Under construction

DEVAKI COMPLEX

by DILIP DHARMAJI WAVHAL

GAT NO 2971, Alefata (N.V.), 412411

Dec 2018
Possession
23.6%
Built
1
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2018) has passed with construction at 23.6%.

Official RERA facts

Registration
P52100009441
Status
Ongoing
Stage
Certificate Signed
Possession
December 2018
Construction
23.6% complete
Units sold
0 of 0

RERA complaint record1 record

  • ComplaintCC1250068927 Feb 2025
    Rajiv Govind Hadawale vs DILIP DHARMAJI WAVHAL

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supply20%
Sewerage (Chamber, Lines, Septic Tank , STP)20%
Storm Water Drainsnot started
Landscaping & Tree Planting10%
Electrical meter room, sub-station, receiving station10%

Building & registration

RERA registered
Aug 2017
Floors
6

Buyer community

Connect with other buyers and owners of DEVAKI COMPLEX โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching DEVAKI COMPLEX. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.