Under construction

FORTUNE PLAZA PHASE IIMahaRERA P52100009565

by VENKATESH LAXMI DEVELOPERS

57/11, 411014

Jun 2022
Possession
42.3%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2018, now proposed Jun 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2022) has passed with construction at 42.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2022 per the RERA filing.

Official RERA facts

Registration
P52100009565
Status
Ongoing
Stage
Certificate Signed
Possession
June 2022originally December 2018
Construction
42.3% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Open Parking30%

Building & registration

RERA registered
Aug 2017
Floors
4

Buyer community

Connect with other buyers and owners of FORTUNE PLAZA PHASE II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching FORTUNE PLAZA PHASE II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.