Jun 2027
Possession
69.1%
Built
1
Complaints
32
Units
High risk
- Possession delayed ~7 yrs. Originally promised Sept 2020, now proposed Jun 2027 per the RERA filing.
Official RERA facts
- Registration
- P52100010029
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2027originally September 2020
- Construction
- 69.1% complete
- Units sold
- 17 of 32
RERA complaint record1 record
- ComplaintCC00500000029019722 Jan 2024Ganapati Pandurang Powar vs Kapila DevelopersOrder of Ganapati Powar vs Kapila Dev.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting70%
Street Lightingdone
Water conservation /Rain water harvestingdone
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station70%
Aggregate area of recreational Open Spacenot started
Open Parkingdone
Building & registration
- RERA registered
- Aug 2017
- Floors
- 8
- Unit mix
- 32 res ยท 0 comm
- Architect
- AR SANGRAM SALUNKE
Buyer community
Connect with other buyers and owners of KAPILA VASTU โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching KAPILA VASTU. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.