Under construction

Yes Residency

by Yemul& Sancheti Associates

84/13 26 14, Hadapsar, 411028

Jun 2024
Possession
79.5%
Built
2
Complaints
0
Units
High risk
  • Possession delayed ~5 yrs. Originally promised Dec 2018, now proposed Jun 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2024) has passed with construction at 79.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2024 per the RERA filing.

Official RERA facts

Registration
P52100010630
Status
Ongoing
Stage
Certificate Signed
Possession
June 2024originally December 2018
Construction
79.5% complete
Units sold
0 of 0

RERA complaint record2 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supply70%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Street Lightingnot started
Solid Waste Management And Disposal90%
Water conservation /Rain water harvesting80%
Fire protection and fire safety requirements75%
Electrical meter room, sub-station, receiving station50%

Building & registration

RERA registered
Aug 2017
Floors
13

Buyer community

Connect with other buyers and owners of Yes Residency โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Yes Residency. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.