Under construction

Avneesh

by Sai Nirmiti Promoters & Builders

Sr. No 8/2, Pimpri Waghere, 411017

Oct 2020
Possession
81.8%
Built
1
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Oct 2020) has passed with construction at 81.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2020 per the RERA filing.
Santacruz / KharUltra-luxury

Bandra's quieter northern neighbour โ€” low-rise lanes going boutique.

Growth drivers:
Society redevelopment, airport and BKC equidistance.
Who buys here:
Professionals wanting Bandra adjacency with less noise.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P52100011082
Status
Ongoing
Stage
Certificate Signed
Possession
October 2020
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Energy managemcnt50%
Electrical meter room, sub-station, receiving station50%
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
5

Buyer community

Connect with other buyers and owners of Avneesh โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Avneesh. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.