PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

DAFFODILS K BUILDINGMahaRERA P52100011485

by VISHHRAM DEVELOPERS

252P, 169, 170, 320, 321, 322, 323, SOMATANE, 410506

Dec 2023
Possession
81.8%
Built
1
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 81.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2023 per the RERA filing.

Official RERA facts

Registration
P52100011485
Status
New
Stage
Certificate Signed
Possession
December 2023
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Water50%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station50%
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
8

Buyer community

Connect with other buyers and owners of DAFFODILS K BUILDING โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching DAFFODILS K BUILDING. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.