PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

INSIGNIA - PHASE IIMahaRERA P52100011802

by M/s. K N ASSOCIATES

Survey No 46/1/1 And S.No 46/2/1, Baner, 411045

Dec 2018
Possession
64.8%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2018) has passed with construction at 64.8%.

Official RERA facts

Registration
P52100011802
Status
Ongoing
Stage
Certificate Signed
Possession
December 2018
Construction
64.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths70%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Planting60%
Street Lighting60%
Water conservation /Rain water harvestingdone

Building & registration

RERA registered
Aug 2017
Floors
5

Buyer community

Connect with other buyers and owners of INSIGNIA - PHASE II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching INSIGNIA - PHASE II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.