BOUGAIN VILLA - CLUSTER 1MahaRERA P52100011902
Gat No 623,631,637,630,656, Pasure, 412206
Dec 2031
Possession
0%
Built
0
Complaints
41
Units
High risk
- Possession delayed ~10 yrs. Originally promised Dec 2021, now proposed Dec 2031 per the RERA filing.
Official RERA facts
- Registration
- P52100011902
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2031originally December 2021
- Construction
- 0% complete
- Units sold
- 29 of 41
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Street Lightingdone
Community Buildingsdone
Electrical meter room, sub-station, receiving stationdone
Building & registration
- RERA registered
- Aug 2017
- Floors
- 1
- Unit mix
- 40 res ยท 1 comm
- Architect
- GROUP PHI ARCHITECTS & DESIGNERS
Buyer community
Connect with other buyers and owners of BOUGAIN VILLA - CLUSTER 1 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching BOUGAIN VILLA - CLUSTER 1. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.