Rajyog phase II -B WingMahaRERA P52100013599

by Rajadhiraj Developers

Sr no 6/10 6/11 6/18 3/1 to 4/1/1, AMBEGAON Bk, 411046

Jan 2021
Possession
57.3%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Jul 2019, now proposed Jan 2021 per the RERA filing.
  • Possession date passed. The proposed possession date (Jan 2021) has passed with construction at 57.3%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jan 2021 per the RERA filing.

Official RERA facts

Registration
P52100013599
Status
Ongoing
Stage
Certificate Signed
Possession
January 2021originally July 2019
Construction
57.3% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths10%
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Oct 2017
Floors
10

Buyer community

Connect with other buyers and owners of Rajyog phase II -B Wing โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Rajyog phase II -B Wing. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.