SHRI RENUKA ASSOCIATES VANSHRI MAMURDI PROJECT
SR NO 13/1A/1 PART MAMURDI PUNE, NEAR MAVAL GATE HOTEL, 412101
- Possession delayed ~4 yrs. Originally promised Oct 2020, now proposed Dec 2024 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 18.2%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2024 per the RERA filing.
Official RERA facts
- Registration
- P52100013840
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2024originally October 2020
- Construction
- 18.2% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Oct 2017
- Floors
- 10
Buyer community
Connect with other buyers and owners of SHRI RENUKA ASSOCIATES VANSHRI MAMURDI PROJECT โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SHRI RENUKA ASSOCIATES VANSHRI MAMURDI PROJECT. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.