Under construction

KohinoorMahaRERA P52100013890

by Oxford Properties ( Kondhwa Project)

S NO 4A 1 HISSA NO 10 AND 11 AND S NO 4A 1A1 HISSA NO. 12A N 12B, KONDHWA KHURD, KONDHWA, 411048

Mar 2023
Possession
67.3%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2023) has passed with construction at 67.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2023 per the RERA filing.

Official RERA facts

Registration
P52100013890
Status
New
Stage
Certificate Signed
Possession
March 2023
Construction
67.3% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)70%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Oct 2017
Floors
19

Buyer community

Connect with other buyers and owners of Kohinoor โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Kohinoor. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.