Under construction

HILLVEW RESIDENCY PHASE I PROJECT III BLDG N AND O

by KUMAR BEHARAY PROPERTIES LLP

69/5-B/2, 69/8/1, 70/1 TO 17 A1, BEHIND MAHATMA SOCIETY KOTHRUD, 411038

Dec 2023
Possession
90.9%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 90.9%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2023 per the RERA filing.

Official RERA facts

Registration
P52100014885
Status
New
Stage
Certificate Signed
Possession
December 2023
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Jan 2018
Floors
18

Buyer community

Connect with other buyers and owners of HILLVEW RESIDENCY PHASE I PROJECT III BLDG N AND O โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching HILLVEW RESIDENCY PHASE I PROJECT III BLDG N AND O. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.