Under construction

ECO SHOPPY

by NAMRATA DEVELOPERS PVT. LTD

SURVEY NO. 27/A/1/2B, HISSA NO. 1/2/3/4, s, 410507

Apr 2021
Possession
80%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Apr 2021) has passed with construction at 80%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2021 per the RERA filing.

Official RERA facts

Registration
P52100015225
Status
New
Stage
Certificate Signed
Possession
April 2021
Construction
80% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Water50%
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving station80%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Feb 2018
Floors
3

Buyer community

Connect with other buyers and owners of ECO SHOPPY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ECO SHOPPY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.