๐Ÿ—๏ธ
Under construction

TREEMOUNTMahaRERA P52100015410

by RENAISSANCE ENTERPRISES

Survey No 69, Hissa No 3/1, Dabhade, 410507

Jun 2018
Possession
81%
Built
1
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Jun 2018) has passed with construction at 81%.

Official RERA facts

Registration
P52100015410
Status
New
Stage
Certificate Signed
Possession
June 2018
Construction
81% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths30%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)60%
Storm Water Drains50%
Landscaping & Tree Planting40%
Street Lighting62%
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting40%
Energy managemcnt60%
Fire protection and fire safety requirements60%
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Compound Walldone
Under Ground Water Tanksdone
Water Pumpsnot started

Building & registration

RERA registered
Feb 2018
Floors
10

Buyer community

Connect with other buyers and owners of TREEMOUNT โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching TREEMOUNT. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.