PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

BENCHMARK

by NG RATHI DEVELOPERS

5/2A/1, 6/2A/1, 6/2B, 6/2A/2/1, 6/2A/5, 6/1/2B/, 6/2C, UNDRI, 411060

Mar 2022
Possession
90.9%
Built
1
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2022) has passed with construction at 90.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2022 per the RERA filing.

Official RERA facts

Registration
P52100015705
Status
New
Stage
Certificate Signed
Possession
March 2022originally March 2021
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Mar 2018
Floors
6

Buyer community

Connect with other buyers and owners of BENCHMARK โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching BENCHMARK. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.