- 21 RERA complaints. 21 complaint records are disclosed against this project on MahaRERA.
Official RERA facts
- Registration
- P52100016536
- Status
- โ
- Stage
- โ
- Possession
- โ
- Construction
- โ
- Units sold
- โ
RERA complaint record21 records
- ComplaintCC1250175028 May 2025Vitthal Shrimant Padase vs OM SAI DEVELOPERSOrder on record: Common Order of Om Sai Developers- 19 complaints (2).pdf
- ComplaintCC1250175128 May 2025Bhor Sambhaji Hanumant vs OM SAI DEVELOPERSOrder on record: Common Order of Om Sai Developers- 19 complaints (2).pdf
- ComplaintCC1250173627 May 2025Dnyaneshwar Appaji Gade vs OM SAI DEVELOPERSOrder on record: Common Order of Om Sai Developers- 19 complaints (2).pdf
- ComplaintCC1250173727 May 2025Prakash Mahadev Khamkar vs OM SAI DEVELOPERSOrder on record: Common Order of Om Sai Developers- 19 complaints (2).pdf
- ComplaintCC1250173527 May 2025PRASHANT HANMANT PISAL vs OM SAI DEVELOPERSOrder on record: Common Order of Om Sai Developers- 19 complaints (2).pdf
- ComplaintCC1250173327 May 2025Sandeep Balkrishna Jadhav vs OM SAI DEVELOPERSOrder on record: Common Order of Om Sai Developers- 19 complaints (2).pdf
- ComplaintCC1250168524 May 2025Anil krishna Ingale vs OM SAI DEVELOPERSOrder on record: Common Order of Om Sai Developers- 19 complaints (2).pdf
- ComplaintCC1240111313 Dec 2024Ashwini Chintan Joshi vs OM SAI DEVELOPERSOrder on record: Common Order of Om Sai Developers- 19 complaints (2).pdf
- ComplaintCC1240109411 Dec 2024Ambadas Eknath Ingulkar vs OM SAI DEVELOPERSOrder on record: Common Order of Om Sai Developers- 19 complaints (2).pdf
- ComplaintCC1240109310 Dec 2024MAHESH MOHANRAO NAMDE vs OM SAI DEVELOPERSOrder on record: Common Order of Om Sai Developers- 19 complaints (2).pdf
- ComplaintCC124010718 Dec 2024Santosh Devidas Bhagat vs OM SAI DEVELOPERSOrder on record: Order of Santosh Bhagat.pdf
- ComplaintCC124010708 Dec 2024Uma Ashok Ingawale vs OM SAI DEVELOPERSOrder on record: Order of Uma Ingawale.pdf
- ComplaintCC124010616 Dec 2024Sachinkumar Gangadhar Yellewad vs OM SAI DEVELOPERSOrder on record: Common Order of Om Sai Developers- 19 complaints (2).pdf
- ComplaintCC124010355 Dec 2024Shubham Dighambar Kolhe vs OM SAI DEVELOPERSOrder on record: Common Order of Om Sai Developers- 19 complaints (2).pdf
- ComplaintCC1240093830 Nov 2024Mukund Shantaram Inamdar vs OM SAI DEVELOPERSOrder on record: Common Order of Om Sai Developers- 19 complaints (2).pdf
- ComplaintCC1240091528 Nov 2024Mehul Jai Mota vs OM SAI DEVELOPERSOrder on record: Common Order of Om Sai Developers- 19 complaints (2).pdf
- ComplaintCC1240091628 Nov 2024Chirag Jai Mota vs OM SAI DEVELOPERSOrder on record: Common Order of Om Sai Developers- 19 complaints (2).pdf
- ComplaintCC1240092728 Nov 2024Sagar Mukund Inamdar vs OM SAI DEVELOPERSOrder on record: Common Order of Om Sai Developers- 19 complaints (2).pdf
- ComplaintCC1240091928 Nov 2024shubham rajesh kudale vs OM SAI DEVELOPERSOrder on record: Common Order of Om Sai Developers- 19 complaints (2).pdf
- ComplaintCC1240091428 Nov 2024Prashant Rajaram Patil vs OM SAI DEVELOPERSOrder on record: Common Order of Om Sai Developers- 19 complaints (2).pdf
- ComplaintCC1240078915 Nov 2024Akshata Jagadish Jadhav vs OM SAI DEVELOPERSOrder on record: Common Order of Om Sai Developers- 19 complaints (2).pdf
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsdone
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Water50%
Solid Waste Management And Disposal20%
Water conservation /Rain water harvesting80%
Energy managemcntnot started
Fire protection and fire safety requirements75%
Electrical meter room, sub-station, receiving station75%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Building & registration
- RERA registered
- May 2018
- Floors
- 13
- Unit mix
- 126 res ยท 0 comm
Buyer community
Connect with other buyers and owners of RAVINANDA AAMRAI PHASE 1 BUILDING C โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching RAVINANDA AAMRAI PHASE 1 BUILDING C. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.