NYATI ERICAMahaRERA P52100017027

by NYATI BUILDERS PRIVATE LIMITED

SR NO 23 HISSA NO 5, UNDRI, 411060

Dec 2021
Possession
74%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 74%.
  • Promised amenities not started. Swimming Pool is at 0% build with possession due Dec 2021 per the RERA filing.

Official RERA facts

Registration
P52100017027
Status
New
Stage
Certificate Signed
Possession
December 2021
Construction
74% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths28%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drains31%
Landscaping & Tree Planting8%
Street Lighting22%
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposal80%
Water conservation /Rain water harvesting68%
Energy managemcnt84%
Fire protection and fire safety requirements78%
Electrical meter room, sub-station, receiving station43%
Open Parkingnot started
Gas Bank51%
Swimming Poolnot started

Building & registration

RERA registered
Jul 2018
Floors
12

Buyer community

Connect with other buyers and owners of NYATI ERICA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching NYATI ERICA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.