PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

UMA DARSHAN PHASE IIMahaRERA P52100017054

by VIGHNAHAR DEVELOPERS

142 2, 142 3, RAJGURUNAGAR, 410505

Dec 2025
Possession
50.2%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Jun 2023, now proposed Dec 2025 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 50.2%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2025 per the RERA filing.

Official RERA facts

Registration
P52100017054
Status
New
Stage
Certificate Signed
Possession
December 2025originally June 2023
Construction
50.2% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths80%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Jul 2018
Floors
10

Buyer community

Connect with other buyers and owners of UMA DARSHAN PHASE II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching UMA DARSHAN PHASE II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.