Under construction

Gulmohar ApartmentMahaRERA P52100017155

by M/S SHREERAM BUILDERS

Plot No.18, CTS NO 2006 S.NO. 82/1 B, Gulmohar Apartment, OPP SHINDE HIGH SCHOOL, 411009

Oct 2021
Possession
81.8%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Oct 2021) has passed with construction at 81.8%.

Official RERA facts

Registration
P52100017155
Status
New
Stage
Certificate Signed
Possession
October 2021
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Jul 2018
Floors
6

Buyer community

Connect with other buyers and owners of Gulmohar Apartment โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Gulmohar Apartment. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.