Sept 2026
Possession
45.8%
Built
16
Complaints
236
Units
High risk
- Possession delayed ~4 yrs. Originally promised Dec 2022, now proposed Sept 2026 per the RERA filing.
- 16 RERA complaints. 16 complaint records are disclosed against this project on MahaRERA.
- Behind schedule. Possession is due Sept 2026 but construction is only at 45.8%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2026 per the RERA filing.
Official RERA facts
- Registration
- P52100017650
- Status
- New
- Stage
- Certificate Signed
- Possession
- September 2026originally December 2022
- Construction
- 45.8% complete
- Units sold
- 138 of 236
RERA complaint record16 records
- ComplaintCC1260323929 May 2026Minal Tejas Thorat vs Puravankara Limited
- ComplaintCC1260299320 May 2026ANJALI NITIN LATKAR vs Puravankara Limited
- ComplaintCC1260271910 May 2026Trupti Madhukar Rotwadkar vs Puravankara limited
- ComplaintCC126025521 May 2026Kanchan Choudhary vs Puravankara Limited
- ComplaintCC1260252930 Apr 2026Najmul Hussain vs Puravankara Limited
- ComplaintCC1260244526 Apr 2026JITENDRA PANDURANG BARATE vs Puravankara Limited
- ComplaintCC1260243426 Apr 2026KISHOR DEVIDAS PAKHMODE vs Puravankara Limited
- ComplaintCC1260241625 Apr 2026Suryad Hemant Pai vs Puravankara Limited
- ComplaintCC1260240624 Apr 2026Vikrant Hase vs Puravankara Limited
- ComplaintCC1260239423 Apr 2026Nachiket Satish Kshire vs Puravankara Limited
- ComplaintCC1260235721 Apr 2026Bhavesh Gujarathi vs Puravankara Limited
- ComplaintCC1260150818 Mar 2026Tejas Arun Sathe vs Puravankara Limited
- ComplaintCC126012106 Mar 2026Manoj Sharma vs Puravankara Limited12 withdrawal.pdf on MahaRERA
- ComplaintCC126006233 Feb 2026Amit Govindrao Kagwade vs Puravankara Limited
- ComplaintCC125027244 Aug 2025NITIN TULARAM MAHAJAN vs Puravankara LimitedWithdrawal order CC12502724.pdf on MahaRERA
- ComplaintCC1250256926 Jul 2025Arbazali Nazir Khan vs Puravankara Limited
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths52%
Internal Roads & Footpaths52%
Internal Roads & Footpaths52%
Internal Roads & Footpaths52%
Water Supply40%
Water Supply40%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposal25%
Solid Waste Management And Disposal25%
Water conservation /Rain water harvestingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Energy managemcntnot started
Fire protection and fire safety requirements50%
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station25%
Electrical meter room, sub-station, receiving station25%
Open Parkingnot started
Open Parkingnot started
Building & registration
- RERA registered
- Sept 2018
- Floors
- 20
- Unit mix
- 236 res ยท 0 comm
- Architect
- Advantage Architects
Buyer community
Connect with other buyers and owners of Purva Aspire โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Purva Aspire. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.