Under construction

The MpireMahaRERA P52100018184

by EAGLE DEVELOPERS

236, 5A/1,5B/1, 5B/2,, FURSUNGI VILLAGE, 412308

Mar 2022
Possession
61.8%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2022) has passed with construction at 61.8%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Mar 2022 per the RERA filing.

Official RERA facts

Registration
P52100018184
Status
New
Stage
Certificate Signed
Possession
March 2022
Construction
61.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths70%
Water Supply10%
Sewerage (Chamber, Lines, Septic Tank , STP)10%
Storm Water Drainsnot started
Landscaping & Tree Planting20%
Street Lighting20%
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcnt10%
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
ENTRANCE GATE50%

Building & registration

RERA registered
Oct 2018
Floors
17

Buyer community

Connect with other buyers and owners of The Mpire โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching The Mpire. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.